The main dome is almost completed and we are now getting ready to start the Kalash! To carry out the Kalash work, the height of the tower crane must be increased; from the now existing level of 278 feet (85 meters) to 380 feet ( 116 meters).
They are two biggest self standing cranes in the whole of India and they were specially brought to India for this project. They are so tall that in order to secure the stability of the crane at such height, guy rope anchoring work has to be done. Anchoring work consist of installing a tensioned guy rope from a RCC foundation spot to the crane. Four RCC foundation spots have been completed in four directions. These cables have to be precisely at 50 degrees without fault.
This work will be successfully complete in another 15 days and we will then begin the Kalash work!